Country Energy is trialling the use of steel poles in the far west region in an effort to combat the constant damage caused to timber poles by termites.

Regional General Manager, Guy Chick said, "Country Energy has chosen to begin the trial of steel poles in the Far West as powerlines in the Wentworth and Balranald district have always been very susceptible to termites, due to the type of soil and environment surrounding the network."

Around 14 timber poles will be replaced with steel poles over the coming months in the Wentworth and Balranald area and on one of the major powerlines north of Coombah, where termites have been found to have a severe effect.

The completed power poles will deter termites from attacking the poles

Mr Chick explained that steel has the potential to bring significant benefits to the far west electricity network.

"Combating termites is a priority of this trial, though addressing our reliance on a scarce resource like timber is an issue that is being addressed industry wide."

"We currently use concrete poles in our network, but these can weight up to four tonnes each making the transport and handling process a lot more intensive," he said.

Country Energy has a strict asset inspection program that follows a four and a half year cycle, and ensures that the 30,000 poles in the southern region of the far west are well maintained.

"Like painting the Harbour Bridge, just as we finish inspecting and repairing them we start the process all over again. Steel poles have the potential of reducing this cycle, and making the electricity network more secure for our customers," Mr Chick said.

Country Energy has already replaced 10 poles on the Coombah line with steel, and plan to start trialling steel poles in the northern area of the far west region within the next six months.

"We will monitor the use of steel poles over the year or so, and combined with results from other trials that Country Energy is running, we will then make a decision on utilising steel poles across our network area."

Reproduced with permission from Sunraysia Daily, Originally published Saturday, September 23, 2006

Download Far West at Forefront of Trial for Steel Power Poles (295 KB)

 
 

 
Contact Us | Sitemap | Terms and Conditions | Privacy Policy

SURELINE ® BlueScope Steel Limited ABN 16 000 011 058 BlueScope is a trademark of BlueScope Steel Limited

This is an Australian Made product Sureline